CISDI is powering forward with its latest innovation

Date:2019/7/17 Source: CISDI

CISDI is powering forward with its latest innovation

CISDI has successfully developed a power transmission for a 220kV general substation.

It is now in operation at Sinopec-KNPC’s integrated refining and chemical plant in Guangdong.

CISDI is the EPC-based supplier for the substation and the first of its chemical projects.

The substation will supply power for the entire refining and chemical integrated plant, and is the first unit for completion.

Its successful power-on triggers its sub-units and provides a solid foundation for the power distribution sub-centres and regional substations.

The substation can fulfill the very demanding power requirements of the petro-chemical industry thanks to its systematic structural safety, optimisation and advanced configuration.

Half of the substation has been designed as interior installations. The general power distribution building has five floors and also houses auxiliary facilities.

The substation contains four 120MVA transformers and 220kV and 110kV GIS. The system adopts a double-bus sectionalised wiring scheme.

This major project signifies the substantial international co-operation on energy between China and Kuwait, under the Framework Agreement for Oil and Gas Development Co-operation which was signed in 2004.

 

说明: http://3w.cisdi.com.cn/files.upload/20190604_08271464/20190504083005-拼图1.jpg

The exterior and interior of the power-on 220kV general substation for Sinopec-KNPC’s integrated refining and chemical plant in Guangdong